ADIRONDACK Biogas Plant

LocationUSA, New York (state)
Construction Period2022
InputDairy manure
FermenterExisting digester
Gas utilizationBiogas upgrading system 450m³/h
ExtensionExtention of existing agricultural biogas plant, virtual gas pipeline (by truck), digestate heat recovery
Specials 
ResponsibilityBasic evaluation, pre-, draft- and executationplaning, tendering, participating in contract awarding process, site management/project controlling, start-up, training for operator