NEW YORK STATE 2 Biogas Plant
| Location | USA, New York (state) |
| Construction Period | 2022 |
| Input | Dairy manure |
| Fermenter | Steel tank 8,000 m³ |
| Gas utilization | Biogas upgrading |
| Extension | |
| Specials | Agricultural biogas plant with biogas upgrading: 1 digester, 1 secondary digester with gas holder roof, mesophilic process, digestate heat recovery and dewatering system, external biological desulphurisation |
| Responsibility | Basic evaluation, pre-, draft and execution planning, tendering, participating, in contract awarding process, site management/project controlling, start-up, training for operator |
| News | News: 19.03.2025 Commissioning of seven plants started in the USA.
|