TODENDORF Biogas Plant
| Location | Germany |
| Construction Period | 2002/ 2003 |
| Input | Manure, grass silage |
| Fermenter | Steel tank, 2.400 m3 |
| Gas utilization | Dual fuel co-generator, 2 x 220 kWel |
| Specials | Digester, secondary digester, heat utilisation |
| Responsibility | Basic evaluation, pre-, draft-, approval and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up |
| Download Datasheet | 121 Todendorf englisch 030730.pdf |