FAKLER Biogas Plant
| Location | Germany |
| Construction Period | 2004/2005 |
| Input | Corn silage, grass silage, whole crop silage |
| Fermenter | Concrete Tank 1,100 m3 |
| Gas utilization | Gas engine 250 kWel |
| Specials | Digester, gas holder above sencondary digester, thermophilic operation, heat utilisation |
| Responsibility | Basic evaluation, pre-, draft-, approval and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up |
| Download Datasheet | 574 Fakler englisch 060721.pdf |