GUT ALTENHOF Biogas Plant

LocationGermany
Construction Period2007
InputCorn silage, wheat silage, grass silage
FermenterConcrete Tank 1,500 m3
Gas utilizationGas engine 365 kWel
Extension2012/13: Second CHP and heat grid to the swimming pool; new heat distribution system
SpecialsDigester, secondary digester and storage tank with gas holder roof, thermophilic operation
ResponsibilityBasic evaluation, pre-, draft-, approval and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up